Wulanda Recreation and Convention Centre Update

Wulanda Recreation and Convention Centre Update
15 February 2021

Southern carpark: kerbing works and pavement base completed. Asphalt to be installed soon.

Outdoor 50 metre pool: demolition of stairs and handrails continuing.

Internal pools: excavation work, installation of blockwork and column reinforcement and concreting.

Internal work: completion of loadbearing block walls in readiness for slab brace walls.

Time Courts and Sports Courts: continuation of footings excavation, reinforcement, holding down bolts installation and concrete works.

Creche, offices and foyer: foyer stairs completed ready for concreting.